Build an Estimate

A Project's Estimate is built as a tree — Phase, then Category, then priced Items — with pricing driven by each item's own markup, not a single number typed once.

Getting started

1

Start from the Project's Estimates tab

Open a Project → Estimates tab. Click New Estimate to start one, or click an existing Estimate's Phases button to open its line-item tree in a large dialog — this tree is where all the real work happens.

2

Three levels: Phase, Category, Item

Phase is free text you type per estimate (e.g. "Kitchen," "Site Work") — add one via the Add Phase button, just a description and display order. Category is different — a fixed, admin-managed list (your Cost Database's categories), picked from a dropdown when you add one under a Phase, not typed. Item is the actual priced line, added under a Category.

Worth knowing: the Add Item / Add from Catalog / Use Assembly buttons stay disabled until you've selected a Phase or Category node first — if a button looks greyed out, click into the tree first.

Adding items

1

Three ways to add items

Add Item — pick an existing Cost Item from a dropdown (auto-fills description, unit, and cost) or type everything by hand. Add from Catalog — a checkbox tree of your whole Cost Database; check items, set quantities, click Add Selected Items. Use Assembly — copies every item from a predefined Cost Assembly into the selected Phase/Category in one click.

2

Markup lives on each item, not one shared number

Every item carries four separate markup percentages — Material, Labor, Sub, Equipment — editable in the item's own edit dialog. New items (typed, from the catalog, or from an Assembly) all start at 25% by default.

Important: the Estimate's own header also has a Mark-ups section (Material/Labor/Sub/Equipment %) — but that value is not automatically applied to items. Pricing is calculated strictly from each item's own markup fields, so set or check markup at the item level, not just the header, or your pricing won't reflect what you typed there.
3

Total Only vs. the four-part breakdown

An item is either priced with the full Material/Labor/Sub/Equipment breakdown, or with a single Total Only cost + markup — the two modes are mutually exclusive, entering one clears the other.

4

Allowance items and Special Order

Two checkboxes on an item: Allowance Item (a placeholder budget line, not yet priced from a real vendor) and Special Order. An Allowance item with no Actual Cost set shows as an "unresolved allowance" — and vendor-tagging is blocked on it until that's resolved.

After the Estimate is built

1

Generate an Invoice

Back on the Estimates grid, Generate Invoice becomes enabled once the estimate has an Accepted Date — it creates a real Invoice with one line per estimate item, carrying over cost, markup, and tax.

2

Link it to a Proposal, or request vendor pricing

On a Proposal, use its Estimate-linking grid to attach one or more Estimates — the Proposal's total becomes the sum of whatever's linked. Separately, you can select specific estimate items and a vendor to generate a Quote Request (RFQ) directly, independent of the Proposal/Invoice path.

Toolbar & terminology

1

What the tree's toolbar buttons do

Choose Columns — add fields like Allowance/Special Order flags, unit costs, markups (saved per user). Two checkboxes toggle "Show Ext Cost/Price" and "Show Calculated Price." Update $ refreshes unit costs from the Cost Database without touching any item's markup. From the outer Estimates grid: Print List, Export to Excel, and Print Reports (generates a PDF/Word document like a Preliminary Budgeting Estimate, reviewed before optionally saving to Project Attachments).

Phase Category Allowance Item Special Order Total Only Accepted Date